M7 Naas Bypass
A NEW LEVEL OF EXPERTISE & SERVICE
CLIENT
SIAC-Colas M7 JV
LOCATION
M7, Co. Kildare
START DATE
January 2018
END DATE
April 2018
CONTRACT VALUE
This project consists of the widening of the existing M7 motorway from two lanes to three lanes both eastbound and westbound for approximately 14km, between Junction 9 Naas North, and the M7/M9 interchange at Junction 11. We were brought in on the latter stages of the contract to help achieve the key handover dates. During our time on this project we carried out 2500m of drainage piping at various diameters and depths and all manholes that were went allow with them. As well as this we also install 2500m of 100mm servicing ducting and chambers.