Gort to Tamnamore 110kv Line
A NEW LEVEL OF EXPERTISE & SERVICE
CLIENT
TLI Group
LOCATION
Ballygawley
START DATE
June 2016
END DATE
May 2017
CONTRACT VALUE
This project involved the foundation construction of 0-30 & 30-60 Pylons for the NIE Framework through TLI Group, we constructed the site access roads into each of the towers we were working on, including carrying out any bulk excavations required, putting in field drainage where needed, carrying out temporary and permanent fencing for the tower works during construction and reinstatement works for the farmers who owned the fields after construction, including finish topsoiling, re-planting of hedgerows where required. For the tower constructions we carried out all earthworks for the foundations, including temporary shoring or support were needed, tying of the reinforcing for the bases and concreting them and setting the legs for the pylons.